Skip to main content

Nuclear plant status

Find out which reactors at our nuclear power stations are in service and what they are generating.

Legal disclaimer: although reasonable care has been taken in compiling this information, EDF accepts no liability in respect of any errors, omissions, or inaccuracies contained or referred to in it, or in respect of any use of or reliance on such information by any person for any purpose. Additional information on the availability of our nuclear power stations can be found on the Elexon REMIT page.

Last updated
Generation (MW) data as at

Reactor 1

Turbine Generator 1
625
MW
Status
Nominal full load
Date of next statutory outage
May 2027

Reactor 2

Turbine Generator 2
-17
MW
Shutdown category
Planned
Expected return to service date
April 9 2026
Status
Statutory outage

Last updated
Generation (MW) data as at

Reactor 1

Turbine Generator 1
606
MW
Status
Nominal full load
Date of next statutory outage
May 2026
Turbine Generator 2
601
MW
Status
Nominal full load
Date of next statutory outage
May 2026

Last updated
Generation (MW) data as at

Reactor 7

Turbine Generator 7
-23
MW
Shutdown category
Planned
Expected return to service date
Mar 16 2026
Status
Refuelling and graphite inspection outage
Date of next statutory outage
May 2028

Reactor 8

Turbine Generator 8
421
MW
Status
Raising load following automatic trip
Date of next statutory outage
Sep 2026

Last updated
Generation (MW) data as at

Reactor 1

Turbine Generator 1
0
MW
Shutdown category
Planned
Expected return to service date
March 25 2026
Status
Offline for refuelling
Date of next statutory outage
Apr 2027

Reactor 2

Turbine Generator 2
401
MW
Status
Reduced load due to gas circulator issue

Last updated
Generation (MW) data as at

Reactor 1

Turbine Generator 1
571
MW
Status
Nominal full load

Reactor 2

Turbine Generator 2
-39
MW
Shutdown category
Non planned
Expected return to service date
March 15 2026
Status
Outage extended for unit transformer cabling work
Date of next statutory outage
Jan 2027

Nominal full load refers to the nominal maximum generation in megawatts from a reactor.  The output from a reactor can fluctuate even when at full load for many reasons (e.g. plant conditions, sea water temperatures, operating limits/constraints etc).  Where the output of a reactor is reduced by approximately 10% or more of its maximum, the reason for this will be shown.  Generation figures are net of any imports into the station and may be negative when a unit is not generating.

Return to service dates are provided to the same accuracy as provided to National Grid under the requirements of the Grid Code and refer to the first full day of operation.  Where a return to service date falls within approximately two weeks of the date of this report, the exact date will be shown.  Where a return to service date is expected to fall more than two weeks into the future, the week commencing in which a reactor is due to return to service will be indicated (shown as “w/c”).

Sizewell B, a Pressurised Water Reactor, has one reactor and two turbines and therefore is classified as being “one reactor” and “two units”.  The remainder of the stations are Advanced Gas Cooled Reactors, each having two reactors.  Each of these is therefore  classified as being “two reactors“ and “two units”.

Find out more

Nuclear safety

Our number one priority is safety. Find out about our commitment to Zero Harm.

UK Power stations

Our fleet of nuclear power stations have generated enough low carbon electricity to supply all homes in the UK for more than 18 years.

Female engineer standing outside HPC

An Electric Britain

We've been busier than ever helping cut UK carbon emissions to nothing.