Skip to main content
Menu

Meet the team: Osprey

By Hinkley Point C media team | Posted February 20, 2019

With some of the longest, widest and tallest kit arriving on Site, specialist operator in lift, land, marine and logistics, Osprey is heavily involved with delivering the Project’s critical items to HPC.

The company’s a local expert, headquartered in Somerset. The team has used its local knowledge and industry experience to benefit the Project for the past seven years, working regularly with Tier 1 contractors as either subject matter experts or providing operational support on key parts of the build.

They helped make light work of the jetty construction, establishing a Muster Port facility alongside key stakeholder The Bristol Port Company, with Osprey cranes handling the first jetty piles. The team also accurately positioned the heaviest jetty item – shifting a 200-tonne luffing gantry to the installation vessel. Osprey also moved the massive Tunnel Boring Machine (TBM) components to Site, another example of brilliant teamwork and collaboration.

John O’Connor, Commercial Director for Osprey and HPC Lead, said: “Safely completing the first barge delivery for HPC was a significant milestone that’ll pave the way for future marine deliveries. We worked closely with HPC and Balfour Beatty teams, and the result is a credit to the hard work of everyone involved. We’ve succeeded because of collaboration and a good measure of determination.”

Tom Barrett, HPC Project Manager Tunnels, added: “Working alongside Osprey and Balfour Beatty has created a shared knowledge and expertise that can be used for future works at HPC – particularly an effective chain of communication thanks to regular contact with all Tier contractors.”

Osprey’s Self-Propelled Modular Transporter (SPMT) team is currently working alongside Bylor contractor, Fairport Engineering, moving large conveyor structures onto the jetty.

And the team’s preparing for the future too. It’s recently produced an analysis of the transport routes to Site for all upcoming Abnormal Indivisible Loads (AIL), including critical Nuclear Island components.

Related articles

The polar crane was lifted into place by the world's largest land-based crane, Big Carl.
December 05, 2023

Polar crane installed in first reactor building

Hinkley Point C has released new photos of Big Carl lifting the giant polar crane into the first reactor building.
The Lord-Lieutenant met with workers from the Christian and Muslim communities.
October 13, 2023

Lord-Lieutenant of Somerset visits Hinkley Point C

His Majesty’s Lord-Lieutenant of Somerset visited Hinkley Point C in Bridgwater today (Friday 13th October) to meet with the project’s chaplaincy team and members of the workforce from the Christian and Muslim communities.
Image of the turbine hall girder being delivered to the Hinkley Point C site
September 21, 2023

First of two giant Turbine Hall crane girders successfully delivered to site

The first of two giant Turbine Hall crane girders was recently successfully delivered to the Hinkley Point C site.