Skip to main content
Menu
Image of unit 1 on the Hinkley Point C site from above

It’s all go…

Posted October 27, 2023

Seven years ago Hinkley Point C received its Final Investment Decision (FID), which gave the go-ahead for construction to start. Here are a few of the highlights between then and now.

2016

Hinkley Point C got the green light from the government to start work on the first new nuclear power station in a generation.

Image of workers on the earthworks of the Hinkley Point C project in 2016

2017

The main civil engineering works contractor, Bylor, completed the first pour of nuclear safety concrete in the galleries. This concrete pour formed the foundations of the underground technical galleries and the service tunnel network.

Image of Hinkley Point C workers on site on 2017

2018

Hinkley Campus opened its doors in June 2018. Consisting of 15 blocks and 510 bedrooms, the campus was the first purpose-built accommodation site for team members working on the project. This was soon followed by Sedgemoor Campus in Bridgwater, which launched later in the year.

Image of people opening the new Hinkley Point C campus in 2018

2019

Hinkley Point C launched its first annual socio-economic report, which tracked the significant social and economic benefits delivered by the project.

Image showing the front cover of the Hinkley Point C's first socio-economic report document

2020

The crane named Big Carl successfully lifted the first reactor’s first steel liner into place on Unit 2’s Nuclear Island, taking lessons learned from the Unit 1 lift in 2019.

Image showing 'Big Carl' the crane lifting one of the rings into place.

2021

Hinkley Point C trained 750 apprentices, three quarters of the way to its target of creating 1,000 apprenticeships during the project’s construction phase. This milestone was reached in 2022, well ahead of schedule. Today, apprenticeship opportunities are available across the project in a huge variety of specialisms.

Image showing apprentices learning their trade.

2022

The installation of six large structures – known as heads – on the Bristol Channel seabed was completed safely and successfully. The heads make up a vital part of the site’s cooling water system.

Image of the intake heads being lifted and placed in the bottom of the Bristol channel.

2023

A significant milestone is still to come. Later this year, the domed roof will be carefully lifted on top of the first reactor building.

Image of unit 1 on the Hinkley Point C site from above

Take a behind-the-scenes tour of Hinkley Point C with this latest project progress video.

Related articles

Image showing the entrance of one of the tunnels at Hinkley Point C.
October 27, 2023

Tunnel blessing tradition

The construction of Hinkley Point C’s water-cooling tunnels needs meticulous planning and accuracy. But did you know that before the work begins, a ceremony is performed to ‘bless’ the tunnelling work?
Image of Bridgwater carnival
October 27, 2023

Celebrating six years of impact

Since 2017, the HPC Community Fund has proudly granted a remarkable £15 million to support local projects and initiatives. Discover how this funding is making a meaningful difference.