View of Reactor 1 nuclear island

Two years after contracts were signed, HPC continues to power ahead

By EDF | Posted September 27, 2018
  • New pictures and numbers show huge scale of construction since 2016
  • Project on track for next major milestone in 2019
  • UK contractors sign up to new alliance for next phase
  • Innovative collaboration boosts UK industrial expertise and aims to create specialist manufacturing skills in Britain

​Download new photographs and film footage here

Two years after Hinkley Point C was fully launched, the scale of construction and progress has been revealed by the release of new photographs and film footage of the project.

More than 3,200 people are now at work building the new nuclear power station in Somerset. The project is on track for its next major milestone in 2019 – the completion of the 4,500 tonne concrete platform on which the reactor buildings sit. This significant moment for the project is known as “J-0” and has been underpinned by the successful completion of the final design for the work.

The project is also setting its sights further ahead with preparation for the MEH phase (Mechanical, Electrical and HVAC - heating, ventilation and air conditioning).  Today (Thursday) four major UK contractors signed the “MEH Alliance” to work together on the complex installation of cabling and pipework in the power station’s 2,500 rooms.  The innovative approach means that Altrad, Balfour Beatty Bailey, Cavendish Nuclear and Doosan Babcock will pool their expertise to work as a single entity.  The alliance aims to create new industrial capacity and jobs by manufacturing specialist pipework in Britain.

Full construction at Hinkley Point C got underway after EDF, its Chinese partner, CGN, and the UK Government, signed final contracts in September 2016.  The power station will supply the UK with reliable low carbon electricity to meet 7% of the country’s needs. The project is mobilised for an objective of initial delivery for unit 1 at the end of 2025.

Hinkley Point C update

  • Work is advancing on reactor one with completion of its pre-stressing gallery:  this structure sits below the reactor unit and will help to strengthen the main reactor building. Work on reactor two has also begun
  • ‘Deep dig’ is complete for Unit 1: this vast excavation is 21m below sea level and will contain the 54m tall water pumping station
  • 750 metres of underground concrete galleries are ready: these are the channels to house cables and pipes
  • A 500m Jetty has been built to import aggregates by sea, minimising the environmental impact of construction
  • Concrete production has already topped 200,000 cubic metres and. 5.3 million cubic metres of earth have been moved
  • Work will be completed this year on the 760m sea wall. At 13.5m tall, it has been designed  to cope with rising sea levels for the plant’s lifetime
  • The first accommodation campus opened on schedule with 510 beds, a restaurant and gym. Using innovative pre-fabrication techniques, it was installed in just 8 months.
  • £10.6bn of contracts have been awarded with £1.3bn in the South-West and 64% of the project value is being built with UK firms
  • 250 of 1,000 apprentices have been hired and 400 schools have taken part in STEM education events

Hinkley Point C Managing Director, Stuart Crooks said: “Everyone working on the project should be proud of what they have achieved so far.  Unions, contractors and suppliers are successfully working together with a complete focus on quality and safety.  Innovation and experience from other projects is helping us boost productivity and get ready for the next stages. I am also proud of the positive impact that Hinkley Point C is having on the South-West. We are determined to create a positive legacy here for people, communities, jobs and skills.”

Nuclear Energy Minister Richard Harrington said: “Hinkley Point C marks a significant step forward in our transition to a clean, low-carbon energy system, powering nearly six million homes for around 60 years while helping us meet our climate change commitments.” 

“The project is making good progress and is on track to meet its next major milestone, creating more than 25,000 job opportunities. Nuclear has an important role to play in the UK’s energy future. The Government demonstrated its commitment to new nuclear through the Industrial Strategy Nuclear Sector Deal and commissioning Hinkley Point C – the first new nuclear power station in a generation.”

EDF Energy CEO Simone Rossi said:  “Hinkley Point C is making good progress and we are determined to honour the trust put in us to build it.  Now the nuclear industry has been restarted, there is a unique opportunity to reduce costs for a follow-on project at Sizewell C.”

CGN UK CEO Zheng Dongshan said: “We are delighted to make our contribution in the form of the expertise we have developed from the successful delivery of the EPR technology at Taishan.  The long term industrial partnerships forged at Hinkley Point C will provide the foundations on which the UK’s future nuclear power stations are built.”

Downloads

View across site
View across site
Site engineer scanning rock face concrete spray prior to nailing at the sea wall
Site engineer scanning rock face concrete spray prior to nailing at the sea wall
HPC site August 2018. View of concrete batching plants.
HPC site August 2018. View of concrete batching plants.
View of work completed on the technical galleries
View of work completed on the technical galleries
Excavation at Hinkley Point C
Excavation at Hinkley Point C
The 510-bed onsite accommodation campus
The 510-bed onsite accommodation campus

For more information

Gordon Bell
Senior External Communications Manager – Nuclear New Build
(T) 01278 484 032
(M) 07843 218 088
gordon.2.bell@edf-energy.com

About EDF

EDF is driving the transition towards An Electric Britain – a secure, affordable, low-carbon future for everyone. As Britain’s biggest generator of zero carbon electricity, we are investing more than £100 million weekly in Britain’s electricity infrastructure. We supply millions of customers with electricity and help homes and businesses switch to electricity for heating, transport and industrial processes.

We operate five nuclear power stations and more than 35 onshore wind farms and three offshore wind farms. Since 2009, EDF has invested almost £9 billion in the nuclear fleet to improve reliability and extend station lifetimes. The five generating stations currently supply about 12% of the UK’s electricity demand.

EDF is building the UK's nuclear renaissance with the construction of a new nuclear power station at Hinkley Point C. We are a minority investor (12.5%) in and major supplier to a replica plant at Sizewell C in Suffolk. Hinkley Point C and Sizewell C will provide low carbon electricity to meet 14% of UK demand and power around 12 million homes. EDF Group companies Framatome and Arabelle Solutions have a presence in the UK and manufacture critical equipment such as reactor pressure vessels and turbines.

EDF is enabling its 5 million customers, both in business and at home, to choose electric solutions that save cash and carbon, whether it is buying an electric car, generating and storing electricity, selling energy back to the grid or installing solar panels or a heat pump. In 2025, EDF’s Customers business was ranked as one of the Sunday Times’s Best Place to Work.

It is also one of the UK’s leading developers of renewable energy through EDF power solutions UK and Ireland. We have more than 2GW of renewable generation in operation and over 10GW in construction, planning and development across a range of technologies including onshore and offshore wind, solar and battery storage.

We are one of the largest suppliers to British business and a leading supplier of innovative energy solutions that are helping businesses become more energy independent. In addition, the company’s energy services business, Dalkia, one of the UK and Ireland’s largest technical service providers.

Related articles

Sea trials have shown that a new acoustic fish deterrent developed for Hinkley Point C is highly effective.
February 10, 2026

Trials show that Hinkley Point C’s Acoustic Fish Deterrent is Highly Effective 

Sea trials carried out by Swansea University have shown that an acoustic fish deterrent developed for Hinkley Point C is highly effective. The innovative use of ultrasound technology has been shown to keep target fish species away from the power station’s water intakes. 
Hinkley Point C’s second nuclear reactor has arrived in Somerset
January 12, 2026

Hinkley Point C takes another step forward as its second nuclear reactor arrives in Somerset

The twin nuclear power station at Hinkley Point C has taken delivery of its second nuclear reactor. The first arrived in 2023 and is already installed and welded in place on Unit 1 of the power station.
Hinkley Point C Site at night from above
December 08, 2025

NEW VIDEO: Hinkley Point C in 2025

Hinkley Point C has today unveiled its End of Year film, offering a rare glimpse into the work that happens after dark on Britain’s biggest infrastructure project.