Two years after contracts were signed, HPC continues to power ahead

By EDF | Posted September 27, 2018
  • New pictures and numbers show huge scale of construction since 2016
  • Project on track for next major milestone in 2019
  • UK contractors sign up to new alliance for next phase
  • Innovative collaboration boosts UK industrial expertise and aims to create specialist manufacturing skills in Britain

​Download new photographs and film footage here

Two years after Hinkley Point C was fully launched, the scale of construction and progress has been revealed by the release of new photographs and film footage of the project.

More than 3,200 people are now at work building the new nuclear power station in Somerset. The project is on track for its next major milestone in 2019 – the completion of the 4,500 tonne concrete platform on which the reactor buildings sit. This significant moment for the project is known as “J-0” and has been underpinned by the successful completion of the final design for the work.

The project is also setting its sights further ahead with preparation for the MEH phase (Mechanical, Electrical and HVAC - heating, ventilation and air conditioning).  Today (Thursday) four major UK contractors signed the “MEH Alliance” to work together on the complex installation of cabling and pipework in the power station’s 2,500 rooms.  The innovative approach means that Altrad, Balfour Beatty Bailey, Cavendish Nuclear and Doosan Babcock will pool their expertise to work as a single entity.  The alliance aims to create new industrial capacity and jobs by manufacturing specialist pipework in Britain.

Full construction at Hinkley Point C got underway after EDF, its Chinese partner, CGN, and the UK Government, signed final contracts in September 2016.  The power station will supply the UK with reliable low carbon electricity to meet 7% of the country’s needs. The project is mobilised for an objective of initial delivery for unit 1 at the end of 2025.

Hinkley Point C update

  • Work is advancing on reactor one with completion of its pre-stressing gallery:  this structure sits below the reactor unit and will help to strengthen the main reactor building. Work on reactor two has also begun
  • ‘Deep dig’ is complete for Unit 1: this vast excavation is 21m below sea level and will contain the 54m tall water pumping station
  • 750 metres of underground concrete galleries are ready: these are the channels to house cables and pipes
  • A 500m Jetty has been built to import aggregates by sea, minimising the environmental impact of construction
  • Concrete production has already topped 200,000 cubic metres and. 5.3 million cubic metres of earth have been moved
  • Work will be completed this year on the 760m sea wall. At 13.5m tall, it has been designed  to cope with rising sea levels for the plant’s lifetime
  • The first accommodation campus opened on schedule with 510 beds, a restaurant and gym. Using innovative pre-fabrication techniques, it was installed in just 8 months.
  • £10.6bn of contracts have been awarded with £1.3bn in the South-West and 64% of the project value is being built with UK firms
  • 250 of 1,000 apprentices have been hired and 400 schools have taken part in STEM education events

Hinkley Point C Managing Director, Stuart Crooks said: “Everyone working on the project should be proud of what they have achieved so far.  Unions, contractors and suppliers are successfully working together with a complete focus on quality and safety.  Innovation and experience from other projects is helping us boost productivity and get ready for the next stages. I am also proud of the positive impact that Hinkley Point C is having on the South-West. We are determined to create a positive legacy here for people, communities, jobs and skills.”

Nuclear Energy Minister Richard Harrington said: “Hinkley Point C marks a significant step forward in our transition to a clean, low-carbon energy system, powering nearly six million homes for around 60 years while helping us meet our climate change commitments.” 

“The project is making good progress and is on track to meet its next major milestone, creating more than 25,000 job opportunities. Nuclear has an important role to play in the UK’s energy future. The Government demonstrated its commitment to new nuclear through the Industrial Strategy Nuclear Sector Deal and commissioning Hinkley Point C – the first new nuclear power station in a generation.”

EDF Energy CEO Simone Rossi said:  “Hinkley Point C is making good progress and we are determined to honour the trust put in us to build it.  Now the nuclear industry has been restarted, there is a unique opportunity to reduce costs for a follow-on project at Sizewell C.”

CGN UK CEO Zheng Dongshan said: “We are delighted to make our contribution in the form of the expertise we have developed from the successful delivery of the EPR technology at Taishan.  The long term industrial partnerships forged at Hinkley Point C will provide the foundations on which the UK’s future nuclear power stations are built.”

Downloads

View across site
View across site
Site engineer scanning rock face concrete spray prior to nailing at the sea wall
Site engineer scanning rock face concrete spray prior to nailing at the sea wall
HPC site August 2018. View of concrete batching plants.
HPC site August 2018. View of concrete batching plants.
View of work completed on the technical galleries
View of work completed on the technical galleries
Excavation at Hinkley Point C
Excavation at Hinkley Point C
The 510-bed onsite accommodation campus
The 510-bed onsite accommodation campus

For more information

Gordon Bell
Senior External Communications Manager – Nuclear New Build
(T) 01278 484 032
(M) 07843 218 088
gordon.2.bell@edf-energy.com

About EDF

EDF is helping Britain achieve Net Zero by leading the transition to a cleaner, low emission, electric future and tackling climate change. It is the UK’s largest producer of low-carbon electricity(1) and supplies millions of customers with electricity and gas.

It generates low carbon electricity from five nuclear power stations and more than thirty onshore wind farms and two offshore wind farms.

EDF is leading the UK's nuclear renaissance with the construction of a new nuclear power station at Hinkley Point C, and there are advanced plans for a replica at Sizewell C in Suffolk. Hinkley Point C and Sizewell C will provide low carbon electricity to meet 14% of UK demand and power around 12 million homes.

EDF is one of the UK’s largest investors in renewables, with more than 1.5GW of renewable generation in operation and almost 14GW in planning and development across a range of technologies including onshore and offshore wind, solar and battery storage. We are constructing our largest offshore wind farm in Britain – the 450 MW Neart na Gaoithe project in Scotland.

EDF is helping its customers, both in business and at home, take their first steps to sustainably powering their lives. Whether it is buying an electric car, generating and storing electricity, selling energy back to the grid or installing a heat pump. EDF is one of the largest suppliers to British business and a leading supplier of innovative energy solutions that are helping businesses become more energy independent. In addition, the company’s energy services business, Dalkia, is one of the largest technical service providers in the UK and Ireland.

EDF is part of EDF Group, the world’s biggest electricity generator. In the UK, the company employs around 14,000 people at locations across England, Scotland, Wales and Ireland.

Related articles

Apprentice Evie
April 18, 2024

New Skills, Better Jobs: Report Reveals the Positive Impact of Hinkley Point C

New figures published in Hinkley Point C’s 2024 Socio-Economic Impact Report reveal the power of green investment to improve the lives and prospects of people and businesses locally, across Somerset and beyond.
Somerset saltmarsh site
January 04, 2024

Hinkley Point C sets out plan to create Somerset saltmarsh

Hinkley Point C, the new nuclear power station in Somerset, is asking for views on its plans to create more than 800 acres of saltmarsh on the River Parrett.
Big Carl’s spectacular dome lift caps the year
December 15, 2023

Big Carl’s spectacular dome lift caps the year at Hinkley Point C

The dome for Hinkley Point C’s first reactor building has been successfully lifted into place. The major milestone closes the roof on the first reactor building, allowing the first nuclear reactor to be installed next year.