Elec Credit L&G TSG: Step 8 – Check status Electric only install
After 2 mins, press the 'Check Status' button on ToughPad to confirm commissioning process is continuing.
You CANNOT proceed to PPMID if you see:
- 8.1.1 – Commission Device Sync Clock - In Progress / Success /Failure
- Data Model Update – In Progress / Success

If you see any of the above, check our Troubleshooting Guide below.
You CAN proceed to PPMID if you see:
- 1.1.1 - Update Primary Tariff - In Progress / Success
- 6.14.2 - Auxilary Load Control Schedular
- 6.15.1 - Update Security Credentials (KRP)
- 1.6 - Update Payment Mode
- 4.1.1 - Read Instantaneous Import Registers
- 4.1.2 - Read Instantaneous Import TOU Matrices
If you don’t see any of the above, check our Troubleshooting Guide below.
Troubleshooting
8.1.1 – Commission Device Sync Clock – In Progress / Success /Failure
Installer actions to rectify this:
- After 10 minutes, press 'Check Status' - if failure message received change Electric meter and Comms Hub once and go back to Step 2.
- If this doesn’t work, contact TSS for next steps.
Failure/ Error Message received
Installer actions to rectify this:
- Contact TSS.
If a failure message is received when looking for the 1.1.1, 6.14.2, 6.15.1, 1.6, 4.1.1, and/ or 4.1.2:
- If Elec only install, proceed to PPMID.
- If Dual Fuel install, proceed to Gas meter and PPMID.