Elec PAYG L&G TSG: Step 8 – Check status Electric only install
After 2 mins, press the 'Check Status' button on ToughPad to confirm commissioning process is continuing.
You CANNOT proceed to PPMID if you see:
- 8.1.1 – Commission Device Sync Clock - In Progress / Success /Failure
- Data Model Update – In Progress / Success

If you see any of the above, check our Troubleshooting Guide below.
You CAN only proceed if you see either of the below service requests:
- 4.1.1
- 4.1.2
Switch on the CCU and proceed to PPMID.
If you don’t see any of the above, check our Troubleshooting Guide below.
Troubleshooting
8.1.1 – Commission Device Sync Clock – In Progress / Success /Failure
Installer actions to rectify this:
- After 10 minutes, press 'Check Status' - if failure message received change Electric meter and Comms Hub once and go back to Step 2.
- If this doesn’t work or you receive an error message, contact TSS for next steps.