Skip to main content

Hinkley Point C gears up for summer of heavy lifting

By Hinkley Point C media team | Posted July 12, 2022

Hinkley Point C is getting ready for another spectacular engineering feat with the precision placement of 5,000 tonne cooling-water intakes on the seabed.  

Four times longer and twice as high as a double-decker bus, each intake head will be connected to five miles of tunnels used to circulate cooling-water for the new power station.

The first heads have been carefully loaded onto barges at Avonmouth, ready to be towed out to meet two floating heavy lift cranes “Gulliver” and “Rambiz” which will work in tandem to lower the structures into place. Each platform is the size of a football pitch and the cranes have a combined lifting capacity of 7,300 tonnes.

The four “intake” and two “outfall” heads have been built by Balfour Beatty in Avonmouth. Each “loading out” operation, carried out by lifting specialists Mammoet, takes several hours, with the water levels being adjusted at the dock, to ensure the barge can receive the load safely and securely.

Ian Beaumont, Project Director Marine Civils at Hinkley Point C said: “This starts a summer of complex offshore operations, with teams working in collaboration to deliver an incredible feat of engineering. It demonstrates the continued progress being made at Hinkley Point C.”

XXX at Balfour Beatty said: “XXXXXXXXXXXXXX”

The structures will cap the tunnels which will supply Hinkley Point C’s two nuclear reactors with cooling water. The heads are big for a reason. Their size means water will enter the intakes slowly, reducing the number of fish entering the cooling pipes. They are also placed sideways to the tidal flow.  In addition, screens and a fish return system will transfer fish back to sea.  

Hinkley Point C will be the first power station around the Bristol Channel to have fish protection measures in place.

 

Hinkley Point C gears up for summer of heavy lifting

Hinkley Point C is getting ready for another spectacular engineering feat with the precision placement of 5,000 tonne cooling-water intakes on the seabed.

Four times longer and twice as high as a double-decker bus, each intake head will be connected to five miles of tunnels used to circulate cooling-water for the new power station.

The first heads have been carefully loaded onto barges at Bristol Port’s Avonmouth docks, ready to be towed out to meet two floating heavy lift cranes “Gulliver” and “Rambiz” which will work in tandem to lower the structures into place. Each platform is the size of a football pitch and the cranes have a combined lifting capacity of 7,300 tonnes.

The four “intake” and two “outfall” heads have been built by Balfour Beatty in Avonmouth. Each “loading out” operation, carried out by lifting specialists Mammoet, takes several hours, with the water levels being adjusted at the dock, to ensure the barge can receive the load safely and securely.

Ian Beaumont, Project Director Marine Civils at Hinkley Point C said: “This starts a summer of complex offshore operations, with teams working in collaboration to deliver an incredible feat of engineering. It demonstrates the continued progress being made at Hinkley Point C.”
 
Roger Frost, Project Director at Balfour Beatty, said: “Today marks yet another exciting milestone in the construction of Hinkley Point C with the arrival of some of the largest heavy lift vessels in the world, on site. We are now readying ourselves to successfully complete our next feat of engineering: lowering the head structures, which will support the nuclear power station's critical water-cooling system, to the very bottom of the Bristol Channel.”

The structures will cap the tunnels which will supply Hinkley Point C’s two nuclear reactors with cooling water. The heads are big for a reason. Their size means water will enter the intakes slowly, reducing the number of fish entering the cooling pipes. They are also placed sideways to the tidal flow.  In addition, screens and a fish return system will transfer fish back to sea. 

Hinkley Point C will be the first power station around the Bristol Channel to have fish protection measures in place. 

Related articles

The polar crane carefully lowered the reactor into place inside the building.
June 01, 2026

Big Carl lifts Hinkley Point C’s second nuclear reactor into place

Big Carl, the world’s largest crane, has lifted Hinkley Point C’s second nuclear reactor into place before its precision installation inside the reactor building.
Hinkley Point C has spent £5.4 billion with 1,500 businesses across the South West
May 26, 2026

New report measures Hinkley Point C’s positive impact on people and the environment

The scale of Hinkley Point C’s positive impact on people and the economy has been detailed in the Hinkley Point C Socio-economic and Environmental Impact Report 2026.
Hinkley Point C is preparing for the installation of the second reactor.
May 06, 2026

Under the lid - new video tour takes viewers inside Hinkley Point C’s first reactor

Viewers of Hinkley Point C’s latest video update will get to see inside the first reactor at the nuclear power station in Somerset. The behind the scenes tour from Delivery Director Simon Parsons shows the fit out of Unit 1 accelerating and teams getting ready to install the identical second reactor in Unit 2.