Skip to main content

Celebrating the completion of the near 5,000-tonne heads

By Hinkley Point C media team | Posted March 30, 2021

This month the Hinkley Point C Marine Works Team poured the final concrete pours of the six cooling water tunnel heads, completing the work ahead of time.

The first-of-a-kind head structures will cap the intake and outfall tunnels, which are currently being bored by three 1,500-tonne tunnel boring machines under the Bristol Channel.

Each of the four intake heads will be 44 metres long (roughly the length of four double-decker buses), eight metres high and weigh 4,650 tonnes. They will each have 775 tonnes of reinforcement, 125,000 individual reinforcing bars and 1,600m3 of concrete.

The two outfall heads weigh 3,500 tonnes each, with 250 tonnes of reinforcement, 52,000 individual reinforcing bars and 1,100m3 of concrete.

What happens next?

The next phase involves the transportation of the heads out into the Bristol channel which, at 13 metres, has the second highest tidal range in the world.

The heads will be lifted into place in the Channel by the largest marine cranes in the world, Gulliver and Rambiz - vessels that are bigger than a football pitch!

Due to the weight of the intake heads, the two vessels will lift each one in a combined operation known as a “tandem lift”. The tandem lift operation is complex and will be the subject of simulation trials over the course of this coming year. 

The outfall heads, being smaller, will each be lifted into position by one of the cranes.

Related articles

Sea trials have shown that a new acoustic fish deterrent developed for Hinkley Point C is highly effective.
February 10, 2026

Trials show that Hinkley Point C’s Acoustic Fish Deterrent is Highly Effective 

Sea trials carried out by Swansea University have shown that an acoustic fish deterrent developed for Hinkley Point C is highly effective. The innovative use of ultrasound technology has been shown to keep target fish species away from the power station’s water intakes. 
Hinkley Point C’s second nuclear reactor has arrived in Somerset
January 12, 2026

Hinkley Point C takes another step forward as its second nuclear reactor arrives in Somerset

The twin nuclear power station at Hinkley Point C has taken delivery of its second nuclear reactor. The first arrived in 2023 and is already installed and welded in place on Unit 1 of the power station.
December 11, 2025

Nigel Cann appointed as Sizewell C Chief Executive Officer as Julia Pyke steps down

Former Hinkley Point C Delivery Director Nigel Cann has been appointed as Chief Executive Officer for Sizewell C. The move follows the decision of joint Managing Director Julia Pyke to leave the project at the end of the year.