Another key milestone has been achieved at the Hinkley Point C construction site in Somerset, with the completion of the first of three off-shore tunnels needed for the power station’s cooling-water system.

The first Tunnel Boring Machine (TBM), named Mary, reached the end of her 3.5km journey under the Bristol Channel to complete intake tunnel 1 on 9 December 2020.

Roger Frost, Balfour Beatty Project Director, said: “This is a significant achievement - one that marks another step towards the successful delivery of the UK’s landmark nuclear power station, Hinkley Point C. The unrivalled expertise of our people, combined with our state-of-the-art offsite manufacturing facility in Avonmouth, has made it possible for us to break through the first of three off-shore tunnels. I am immensely proud of the commitment everyone has shown.”

The 3.5km-long intake tunnel 1 was mined at a depth of 33m below the Bristol Channel, using one of three TBMs needed for the project. The TBM, named Mary after prominent palaeontologist Mary Anning, was effectively a moving factory operating underground.

As Mary advanced forward she installed concrete rings, each made up of six segments. The tunnel comprises more than 2,300 of these rings, with nearly 14,000 segments needed to complete them. After each ring was placed, the crew then filled the gap behind it with grout. Around 12,000m3 of grout was used in total over the full length of the tunnel.

The nuclear-standard precast segments were produced at Balfour Beatty’s purpose-built manufacturing plant in Avonmouth and transported to site. Some 38,000 segments will be needed to complete the three tunnels.

Mary’s cutter head removed around 340,000 tonnes of earth, which was passed along seven different conveyors, both belt conveyors and a ‘bucket’-style vertical conveyor, down the length of the tunnel, up and out of the deep dig. From here it was loaded onto trucks and used for landscaping on site.

Parts of the TBM will now be stripped and installed on another machine, with the remainder immortalised under the Channel as a time capsule to the incredible feat of engineering.

Attention now turns to the two remaining tunnels for the cooling-water system. Emmeline, the largest of the TBMs, has just started on her 1.8km journey mining the outfall tunnel, and Beatrice, supplemented by equipment from Mary and responsible for intake tunnel 2, is set to launch early next year.

Related articles

Stacy Walker
September 08, 2026

We are Here to Listen: How to Get in Touch with Hinkley Point C

As part of the Hinkley Point C Community Relations team, one of the things I enjoy most about my role is getting out into local communities and talking to people. A question I am often asked is: “How do I actually get in touch with Hinkley Point C?” The good news is, there are lots of ways to contact us – and you don't have to wait for a formal meeting to get involved.
Jack Davies - Quality Assurance Apprentice
August 27, 2026

How is Hinkley Point C benefiting the local community?

Alongside Hinkley Point C’s vital role in providing the country with secure low-carbon electricity, I’m very proud of the significant benefits we provide to our local communities. Maximising the benefits of Hinkley Point C has been a long term collaborative effort, but one which I’m confident will also lead to much longer term opportunity for people and businesses across Somerset and the Sout West.
Parking at Brean Beach
August 14, 2026

Supporting Local Tourism - Free Beach Parking at Brean and Berrow this Summer

Hinkley Point C is helping to make a trip to the seaside a little more affordable this summer by providing free parking at both Brean and Berrow beach car parks. Available throughout the school holidays and into October, the initiative is part of Hinkley Point C’s support for tourism businesses in Brean. The initiative has already proved extremely successful with visitors to the beach more than double the number seen in July last year.