Skip to main content

Update on Hinkley Point C mud dredging

By Hinkley Point C media team | Posted October 02, 2020

Hinkley Point C has decided to carry out a full environmental impact assessment (EIA) as part of its licence application to dispose of mud dredged in the Bristol Channel. This is in addition to a testing plan approved by Natural Resources Wales which goes above and beyond internationally recognised best practice.  Hinkley Point C has decided to carry out the EIA in order to provide the public with further reassurance that all concerns have been addressed. 
 
A licence is required for the planned second phase of dredging off the Somerset site and disposal of mud at the Cardiff Grounds disposal site. Further dredging is needed before placing of the Low Velocity Intake Heads, drilling of shafts for the cooling water system, the installation of a fish recovery and return system and maintenance dredging at the jetty. 
 
Previous testing has shown that this mud is no different to mud found elsewhere in the Bristol Channel and is not classed as radioactive under UK law. Hinkley Point C wants to reassure the public of the safety of this activity and has listened carefully to the concerns and questions that were raised during the first phase of dredging activities. 
 
Hinkley Point C has commissioned CEFAS, the UK Government's marine science experts, to undertake analysis on further sediment samples following approval of the sampling plan, which was subject to public consultation. CEFAS has some of the most advanced radiation testing equipment in the world. 
 
Chris Fayers, head of environment at HPC, said: "For this second phase of dredging, we intend to go further than normal regulatory requirements in order to provide the public with additional reassurance. We have proposed a testing plan that goes above and beyond internationally recognised best practice, with more samples at greater depth and with a greater range of analysis - including tests for pure alpha emitting particles and tritium. 
 
"We also intend to conduct a full Environmental Impact Assessment as part of our disposal licence application. We believe it is right to go beyond technical arguments to provide the necessary public confidence that all concerns have been addressed." 
 
No dredging activity is planned until 2021 and will require approval of the testing plan, analysis of the results, an application being made, and a licence issued. 
 
More information on the dredging can be found here
 

Related articles

The polar crane carefully lowered the reactor into place inside the building.
June 01, 2026

Big Carl lifts Hinkley Point C’s second nuclear reactor into place

Big Carl, the world’s largest crane, has lifted Hinkley Point C’s second nuclear reactor into place before its precision installation inside the reactor building.
Hinkley Point C has spent £5.4 billion with 1,500 businesses across the South West
May 26, 2026

New report measures Hinkley Point C’s positive impact on people and the environment

- £20 million of community grants to 385 local organisations - 19,500 people trained in local “Centres of Excellence” - 1,740 apprentices trained – beating a target of 1,000 - £5.4 billion spent with 1,500 businesses across the South West - New factory opened in North Wales to support the project - Suffolk youngsters learn skills to take home to Sizewell C - 65,000 trees planted and 92 bird species identified around the HPC site
Hinkley Point C is preparing for the installation of the second reactor.
May 06, 2026

Under the lid - new video tour takes viewers inside Hinkley Point C’s first reactor

Viewers of Hinkley Point C’s latest video update will get to see inside the first reactor at the nuclear power station in Somerset. The behind the scenes tour from Delivery Director Simon Parsons shows the fit out of Unit 1 accelerating and teams getting ready to install the identical second reactor in Unit 2.