Skip to main content

Big Carl’s first big lift ends successful year at Hinkley Point C

By Hinkley Point C media team | Posted December 18, 2019

Engineers and lifting specialists at Hinkley Point C worked through the night to successfully complete the first big lift by the world’s largest crane. The 250m tall “Big Carl” crane lifted a 170 tonne prefabricated part of the reactor’s steel containment liner into place at 4.30am on Weds (Dec 18). The lift had been carefully planned to take advantage of a small weather window last night. 

The achievement marked the end of a year where all the milestones for the new nuclear power station were met.  As well as being a great feat of skill, the lift is an important example of innovation. Using lessons learned from EPR construction around the world, the liner section was welded and prefabricated under cover in factory conditions on site to improve quality and lower schedule risk.  



Other major achievements in 2019 included:

  • Completion of the first reactor’s base
  • Start of tunnelling  on the three water cooling intakes  deep beneath the Severn Estuary 
  • Completion of the 760m seawall
  • Hiring of the 500th apprentice  
  • Construction of first permanent buildings above ground 

 

The project is now focused on completing the base of Unit Two in 2020, as planned, 12 months after Unit One. Productivity improvements between the two units show the benefit of replication and using experienced workers repeating the same design. This approach will be used for the proposed near-identical plant at Sizewell C in Suffolk.

The project is also strengthening UK skills by joining in the creation of a national welding centre in Somerset, a UK nuclear Technical Services Organisation in Gloucester and a UK EPR engineering design centre in Bristol. 

Hinkley Point C Managing Director Stuart Crooks said: “The first big lift is another impressive achievement and I want to thank the teams who’ve worked so hard to make this possible. The experience from civil and nuclear construction and operation across the world at Hinkley Point C is first class and I am pleased to say that we have ended 2019 with all milestones achieved.

“We know that Hinkley Point C’s success is essential in the fight against climate change – in a future when renewables and nuclear will be needed to fill an energy gap as we move away from polluting fossil fuels.”

Related articles

Jack Davies - Quality Assurance Apprentice
August 27, 2026

How is Hinkley Point C benefiting the local community?

Alongside Hinkley Point C’s vital role in providing the country with secure low-carbon electricity, I’m very proud of the significant benefits we provide to our local communities. Maximising the benefits of Hinkley Point C has been a long term collaborative effort, but one which I’m confident will also lead to much longer term opportunity for people and businesses across Somerset and the Sout West.
Parking at Brean Beach
August 14, 2026

Supporting Local Tourism - Free Beach Parking at Brean and Berrow this Summer

Hinkley Point C is helping to make a trip to the seaside a little more affordable this summer by providing free parking at both Brean and Berrow beach car parks. Available throughout the school holidays and into October, the initiative is part of Hinkley Point C’s support for tourism businesses in Brean. The initiative has already proved extremely successful with visitors to the beach more than double the number seen in July last year.
Rebar Loading Avonmouth
August 05, 2026

What can this ship teach us about the future of nuclear construction?

This summer, a ship sailed quietly out of Bristol Port bound for Hinkley Point C in Somerset for the last time. After more than 100 sailings, the voyage marked the end of a first-of-a-kind innovation that is transforming nuclear construction in Britain.