Tunnels ready for connection to Bristol Channel

By Hinkley Point C media team | Posted February 15, 2024

Hinkley Point C’s tunnels are ready for the connection to the Bristol Channel to be completed - marking a major step in the construction of the power station’s cooling water system.

Six giant shaft liners have been installed through the intake and outfall heads – ready for final connection to the 5-miles of tunnels.  The 5,000-tonne head structures were lowered onto the seabed in 2022 and will circulate water to the nuclear power station.
 
The 270-tonne liners have been installed 25-meters below sea level and feature a world-first “isolation cap”. This will allow work to be safely carried out in the tunnels during the power station’s construction and operation.
 
Miners will now make the final connection between the tunnels and the liners, which will allow water to start flowing into the power station.
 

Related articles

The polar crane carefully lowered the reactor into place inside the building.
June 01, 2026

Big Carl lifts Hinkley Point C’s second nuclear reactor into place

Big Carl, the world’s largest crane, has lifted Hinkley Point C’s second nuclear reactor into place before its precision installation inside the reactor building.
Hinkley Point C has spent £5.4 billion with 1,500 businesses across the South West
May 26, 2026

New report measures Hinkley Point C’s positive impact on people and the environment

The scale of Hinkley Point C’s positive impact on people and the economy has been detailed in the Hinkley Point C Socio-economic and Environmental Impact Report 2026.
Hinkley Point C is preparing for the installation of the second reactor.
May 06, 2026

Under the lid - new video tour takes viewers inside Hinkley Point C’s first reactor

Viewers of Hinkley Point C’s latest video update will get to see inside the first reactor at the nuclear power station in Somerset. The behind the scenes tour from Delivery Director Simon Parsons shows the fit out of Unit 1 accelerating and teams getting ready to install the identical second reactor in Unit 2.