5 February 2020


Dear SSG Member,

As a member of our community, I wanted to keep you updated on any developments at the power station.

As you are aware, market rules require us to give our most likely view of return to service dates.

Work on the Hunterston Reactor 3 safety case continues and we have revised our latest expectation for its return to service to 10 April 2020 – previously we expected it to return on 28 February.

Reactor 4 came offline in mid-December, following a period of safe and reliable production over several months. We are continuing our detailed graphite inspections and liaising closely with the ONR on the results. We now aim to return the unit to service on 24 April 2020 – previously we expected it to return on 13 March.

I hope this information is useful to you as a member of the Site Stakeholder Group.

Should you wish to ask any questions please feel free to ring the Station on 01294 826000 and ask for our Communications Officer, Nikki Thomson.

Yours sincerely,

John Sandford

Plant Manager

Downloads

Hunterston B power station
Hunterston B power station

Related articles

Torness power station
January 21, 2026

£1.2billion investment across 2026-28 to help boost reliability and output

EDF’s Nuclear Operations business has today (21 January) published its annual fleet update, a review of 2025 performance and an outline of future developments.
People and bouncy castles on grass on a sunny day
May 23, 2025

Fun in the sun for Hunterston B families

The sun shone on Hunterston B, recently, as workers brought their families to the station for a fun day to celebrate their recent decommissioning achievement.
Elevated shot of the Hunterston B charge hall
April 23, 2025

Fuel free at Hunterston B as UK’s first Advanced Gas-cooled Reactor nuclear station completes defueling

Hunterston B power station in North Ayrshire has been defueled on time and on budget. It took less than three years to deliver this key milestone.