Letter to Hunterston Site Stakeholder Group - 19 May 2020

By EDF | Posted May 19, 2020

 

19 May 2020

Dear SSG Member,

As a member of our community, I wanted to keep you updated on any developments at the power station.

As you are aware, market rules require us to give our most likely view of return to service dates.

The safety case for Hunterston B Reactor 3 has been submitted to the ONR for its independent assessment. To support time for this assessment we have revised our latest expectation for its return to service to 13 July2020 – previously we expected it to return on 1 June.

Reactor 4 came offline in mid-December, following a four month run of safe and reliable generation. We now aim to return the unit to service on 27 July 2020 – previously we expected it to return on 15 June.

I hope this information is useful to you as a member of the Site Stakeholder Group. Should you wish to ask any questions please feel free to ring the Station on 01294 826000 and ask for our Communications Officer, Nikki Thomson.

Yours sincerely,  

Paul Forrest

Station Director

 

Downloads

Hunterston B exterior shot
Hunterston B

For more information

Fiona McCall
External Communications Manager (Scotland)
(T) 01355 846281
(M) 07813 232 347
fiona.mccall@edf-energy.com

Related articles

August 06, 2020

Letter to the Hunterston Site Stakeholder Group - 6 Aug 2020

An update to the community on a change of return to service dates for Hunterston B power station
July 02, 2020

Letter to the Hunterston Site Stakeholder Group - 2 July 2020

An update to the community on a change of return to service dates for Hunterston B power station
Hunterston B power station
December 10, 2019

Letter to the Hunterston Site Stakeholder group - 10 December 2019

Hunterston B station director Paul Forrest updates the Site Stakeholder Group on revised dates for return to service of Reactors 3 and 4