Skip to main content
TNUoS

64% TNUoS increase confirmed from April 2026

By Let's Talk Power | Posted February 12, 2026

NESO confirms 60% increase in TNUoS charges from April 2026 

The National Energy System Operator (NESO) has published the final Transmission Network Use of System (TNUoS) tariffs for 2026/27, confirming a sharp 64% increase in transmission network costs for large energy users in the UK from April 2026. 

To help make sense of these changes, we’ve outlined the key information businesses need to know.

Key Headlines 

  • From April 2026, large energy users (businesses and public sector organisations) in the UK face a substantial increase in network costs to fund major upgrades to the UK’s electricity grid.
  • The average £/MWh equivalent residual charge for 2026/27 is now ~£25.70/MWh, up from ~£15.70/MWh today – this represents an increase of roughly £10/MWh year on year.
  • The final tariffs include a small reduction of ~£0.20/MWh compared to the draft tariffs published in December 2025. Whilst this small revision is welcome, the overall 2026 picture confirms a significant rate increase.
  • TNUoS residual charges are recovered on standing charges (£/site/day) but are represented above as average £/MWh equivalents for ease of comparison across different sites where charges will vary 
TNUOS.

What is TNUoS?

Transmission Network Use of System (TNUoS) charges are levied by transmission companies to pay for carrying electricity from power stations through high voltage lines to the local distribution networks. These charges are used to fund the maintenance and upgrading of the transmission network. 

  • Some TNUoS charges vary by region, but the majority are recovered via standing charges that are the same nationally
  • The level of the TNUoS standing charge is determined by the size of a site’s connection and the voltage at which they connect
  • TNUoS currently makes up around 5% of consumer electricity costs, one of the larger items in energy bills 

 TNUoS charges are managed through price controls administered by Ofgem.  

Why is TNUoS increasing? 

With the transition from large, centralised generation assets to more distributed, smaller generators, particularly wind in Scotland and the North, there is a growing need to transport more electricity across the country. This requires more and bigger cables to enable the flow of power from where it is generated to where it is needed. 

At the end of 2024, transmission companies published their business plans for RIIO-ET3, indicating a need to spend around £80bn over five years. That money will ultimately be funded via TNUoS charges on suppliers, although not all of it will be recovered immediately, with Ofgem deciding what is necessary and reasonable.  

Next steps – how we’re supporting customers 

EDF can help businesses, energy consultants and public sector organisations stay ahead by navigating these market changes and managing their exposure to rising network costs.  

Our experts are analysing what this means for customers and are reaching out with tailored guidance and support.   

If you have any questions regarding TNUoS or would like to know the different options and support available, please reach out to your account manager.  

As always, our team will continue to monitor regulatory developments and support customers in navigating the changing cost landscape. For a deeper diver into market changes, join our upcoming webinar Monitor: Non-Energy Costs Explained on Wednesday 17 March at 1 pm.  

Related articles

heatwave header
July 28, 2026

Why electricity prices spiked during the 2026 summer heatwaves

In summer 2026, Great Britain experienced a series of unusually tight electricity system periods during hot, low-wind conditions. Electricity Margin Notices were issued on 24 June, 26 June and 9 July, highlighting that energy system stress is no longer only a winter issue. For business energy users, the lesson is not that the system failed. It did not. The more important point is that hotter weather, lower renewable output, generation availability, interconnector dynamics and demand patterns can combine quickly to move prices and create short-term risk. That makes flexibility, better energy data and a clear procurement strategy increasingly important for organisations that want to manage both cost and resilience.
Corporate Power Purchase Agreement: positively impacts your business and the environment.
July 24, 2026

AR8: What Should Developers, Investors and Energy Buyers Expect from the UK's Next CfD Auction?

As Allocation Round 8 (AR8) of the UK's Contracts for Difference (CfD) scheme progresses, developers, investors and energy buyers are closely assessing what the latest auction could mean for renewable energy deployment, investment and route-to-market strategies. In this article, Tom Hooper, Senior PPA Originator at EDF, explores the key AR8 changes, expected outcomes and why CfDs remain a popular choice for developers, while also examining the growing role of CPPAs, negative price protection and revenue optimisation in helping renewable asset owners maximise value in an increasingly dynamic power market.