Skip to main content
Menu

Hinkley Point C’s offshore work moves into final stages

Posted April 09, 2023

New images show two huge jack-up vessels which have arrived off the coast of Hinkley Point C in Somerset, as the project’s offshore work moves into its final phase.


The vessels, named “Neptune” and “Sea Challenger”, will be used to install vital components for the power station’s cooling water system.

Six vertical shafts will be installed at a depth of more than 20-metres, marking the next stage in connecting the six miles of tunnels with the seabed.

Once installed, miners will dig a horizontal connection between the bottom of the shaft and the tunnel. This is the first part of linking the intake and outfall heads with the tunnels. These 5,000-tonne structures were lowered onto the seabed last summer and will circulate water to the two nuclear reactors.

Often used to build offshore wind farms, the platforms’ cranes have a combined lifting capacity of 1,500 tonnes. At 132m, the “Sea Challenger” is longer than a football pitch, and “Neptune” is 60m long.

Each vessel uses its four “legs” to elevate itself above sea level – so it can operate safely without being impacted by waves and currents.

Work to install the shafts will continue into the Autumn.

 

 

 

Related articles

The polar crane was lifted into place by the world's largest land-based crane, Big Carl.
December 05, 2023

Polar crane installed in first reactor building

Hinkley Point C has released new photos of Big Carl lifting the giant polar crane into the first reactor building.
The Lord-Lieutenant met with workers from the Christian and Muslim communities.
October 13, 2023

Lord-Lieutenant of Somerset visits Hinkley Point C

His Majesty’s Lord-Lieutenant of Somerset visited Hinkley Point C in Bridgwater today (Friday 13th October) to meet with the project’s chaplaincy team and members of the workforce from the Christian and Muslim communities.
Image of the turbine hall girder being delivered to the Hinkley Point C site
September 21, 2023

First of two giant Turbine Hall crane girders successfully delivered to site

The first of two giant Turbine Hall crane girders was recently successfully delivered to the Hinkley Point C site.