Hinkley Point C hits its biggest milestone yet

By Hinkley Point C media team | Posted June 28, 2019

Hinkley Point C has hit its biggest milestone yet on schedule. The completion of the base for the first reactor, known as “J-zero”, means that the construction of the nuclear buildings above ground can now begin in earnest.

The final 9,000m³ of concrete was the largest concrete pour in the UK, beating a record set by the Shard in London.  Reinforced with 5,000 tonnes of Welsh steel, the base has been under construction by the UK-French joint venture of Bouygues-Laing O’Rourke for six months.

The event was due to be marked by a visit from the minister responsible for nuclear energy, Andrew Stephenson MP, who saw the construction site today (Friday June 28) and met apprentices at the National College for Nuclear.

Good progress and efficiency improvements means that the second Hinkley Point C reactor will hit its own J-zero moment in June 2020.

Project update

The construction of the second of Hinkley Point C’s two units is well underway and is already showing the improved efficiency possible when an identical design is repeated. The 12 month separation offers maximum efficiency for the transfer of teams between units.

  • Almost 4,000 people are now working at Hinkley Point C. Half of them are from the local area.
  • Forgings for the pressure vessel and steam generators are underway at Framatome in France and the world’s largest turbine is under construction at GE.
  • The world’s largest crane – the Sarens SGC 250 – is taking shape on site to allow prefabrication of large parts of the nuclear buildings, which improves quality and saves time. This is an innovation informed by experience from previous EPR projects.
  • £1.5bn of contracts have been awarded in the South-West and 64% of the project value is being spent with UK firms.
  • 430 of 1,000 apprentices have been hired and 8,500 people have been trained and assessed at the specially built Construction Skills and Innovation Centre near the site

 

Minister for Nuclear at the Department for Business Energy and Industrial Strategy, Andrew Stephenson said: “This is a huge achievement for Hinkley Point C and a major milestone for the UK’s nuclear new-build industry, which - as a low-carbon electricity source -is key to meeting our ambitious target of net zero emissions by 2050.” 

“The project will not only power nearly six million homes, it will add an enormous boost to the local and national economy, delivering over 25,000 new jobs and securing long-term, well-paid employment – a key step in delivering clean growth as part of our modern Industrial Strategy.”

Hinkley Point C Managing Director, Stuart Crooks said: “I am proud of the talent and achievement of our diverse UK workforce, our unions, our international supply chain and the design team in France. We are benefitting from direct experience from other EPR projects and a partner in CGN which understands the technology and the project.”

Related articles

Hinkley Point C marine works sunrise
February 15, 2024

Tunnels ready for connection to Bristol Channel

Hinkley Point C’s tunnels are ready for the connection to the Bristol Channel to be completed - marking a major step in the construction of the power station’s cooling water system.
site with the dome being put on unit 1 and the words January 2024 update
January 23, 2024

January 2024 project update

Hinkley Point C's Managing Director Stuart Crooks gives an update on the project.
Environment
January 04, 2024

Hinkley Point C sets out plan to create Somerset saltmarsh

Hinkley Point C, the new nuclear power station in Somerset, is asking for views on its plans to create more than 800 acres of saltmarsh on the River Parrett.