Skip to main content
Menu

Celebrating the completion of the near 5,000-tonne heads

By Hinkley Point C media team | Posted March 30, 2021

This month the Hinkley Point C Marine Works Team poured the final concrete pours of the six cooling water tunnel heads, completing the work ahead of time.

The first-of-a-kind head structures will cap the intake and outfall tunnels, which are currently being bored by three 1,500-tonne tunnel boring machines under the Bristol Channel.

Each of the four intake heads will be 44 metres long (roughly the length of four double-decker buses), eight metres high and weigh 4,650 tonnes. They will each have 775 tonnes of reinforcement, 125,000 individual reinforcing bars and 1,600m3 of concrete.

The two outfall heads weigh 3,500 tonnes each, with 250 tonnes of reinforcement, 52,000 individual reinforcing bars and 1,100m3 of concrete.

What happens next?

The next phase involves the transportation of the heads out into the Bristol channel which, at 13 metres, has the second highest tidal range in the world.

The heads will be lifted into place in the Channel by the largest marine cranes in the world, Gulliver and Rambiz - vessels that are bigger than a football pitch!

Due to the weight of the intake heads, the two vessels will lift each one in a combined operation known as a “tandem lift”. The tandem lift operation is complex and will be the subject of simulation trials over the course of this coming year. 

The outfall heads, being smaller, will each be lifted into position by one of the cranes.

Related articles

The Lord-Lieutenant met with workers from the Christian and Muslim communities.
October 13, 2023

Lord-Lieutenant of Somerset visits Hinkley Point C

His Majesty’s Lord-Lieutenant of Somerset visited Hinkley Point C in Bridgwater today (Friday 13th October) to meet with the project’s chaplaincy team and members of the workforce from the Christian and Muslim communities.
Image of the turbine hall girder being delivered to the Hinkley Point C site
September 21, 2023

First of two giant Turbine Hall crane girders successfully delivered to site

The first of two giant Turbine Hall crane girders was recently successfully delivered to the Hinkley Point C site. 
Image of unit 1 on the Hinkley Point C site from above
September 10, 2023

Watch the latest virtual tour of Hinkley Point C

Hinkley Point C has released a new video showing the latest progress in the construction of the new nuclear power station.