2024: A year of monumental achievements at Hinkley Point C

By Hinkley Point C media team | Posted December 13, 2024

One of 12,000 workers building the Hinkley Point C new nuclear power station tells the story of 2024. Lilli, 25, from Taunton joined the project in 2018 as an apprentice and now runs her own team on the site.  She’s one of the many young people building their careers in Somerset and helping boost the area’s economy.  

Hinkley Point C ended the year by installing the first nuclear reactor in Britain for more than 30 years. Work also began installing the world’s largest turbine. Watch our end-of-year film to see these milestones and more and learn about the progress made at Europe's largest construction site in 2024.

Each milestone brings Britain closer to its net zero goals and strengthens our energy security. The power station will supply more than 6m homes with around-the clock low-carbon electricity.

Related articles

The polar crane carefully lowered the reactor into place inside the building.
June 01, 2026

Big Carl lifts Hinkley Point C’s second nuclear reactor into place

Big Carl, the world’s largest crane, has lifted Hinkley Point C’s second nuclear reactor into place before its precision installation inside the reactor building.
Hinkley Point C has spent £5.4 billion with 1,500 businesses across the South West
May 26, 2026

New report measures Hinkley Point C’s positive impact on people and the environment

The scale of Hinkley Point C’s positive impact on people and the economy has been detailed in the Hinkley Point C Socio-economic and Environmental Impact Report 2026.
Hinkley Point C is preparing for the installation of the second reactor.
May 06, 2026

Under the lid - new video tour takes viewers inside Hinkley Point C’s first reactor

Viewers of Hinkley Point C’s latest video update will get to see inside the first reactor at the nuclear power station in Somerset. The behind the scenes tour from Delivery Director Simon Parsons shows the fit out of Unit 1 accelerating and teams getting ready to install the identical second reactor in Unit 2.