Hinkley Point C project cost

By Hinkley Point C media team | Posted May 12, 2016


The cost of the project is £18bn in nominal terms. We have stated this in public many times and this has not changed.

This £18bn includes and has always included a provision for risks and contingencies. If we deliver the project for less, the gain will be shared with customers as part of the CFD gain share mechanism. Customers would not bear the cost of any overruns.

The total equity the two shareholders are committed to provide if necessary includes 15% of additional capacity amounting to £2.7bn.

This does not mean that we anticipate any additional costs beyond £18 bn. It simply reflects normal, prudent good practice for any construction project to know that the money would be available in the case of more extreme scenarios.

We don’t expect to use the additional 15% because we expect that Hinkley Point C will be on time and on budget at £18bn.

Related articles

The polar crane carefully lowered the reactor into place inside the building.
June 01, 2026

Big Carl lifts Hinkley Point C’s second nuclear reactor into place

Big Carl, the world’s largest crane, has lifted Hinkley Point C’s second nuclear reactor into place before its precision installation inside the reactor building.
Hinkley Point C has spent £5.4 billion with 1,500 businesses across the South West
May 26, 2026

New report measures Hinkley Point C’s positive impact on people and the environment

The scale of Hinkley Point C’s positive impact on people and the economy has been detailed in the Hinkley Point C Socio-economic and Environmental Impact Report 2026.
Hinkley Point C is preparing for the installation of the second reactor.
May 06, 2026

Under the lid - new video tour takes viewers inside Hinkley Point C’s first reactor

Viewers of Hinkley Point C’s latest video update will get to see inside the first reactor at the nuclear power station in Somerset. The behind the scenes tour from Delivery Director Simon Parsons shows the fit out of Unit 1 accelerating and teams getting ready to install the identical second reactor in Unit 2.