Built 25% faster - Hinkley Point C's Unit 2 and the "replication effect"

By Hinkley Point C media team | Posted November 16, 2021

Big Carl, the world’s biggest crane has been in action again at Hinkley Point C. It has placed the first huge steel ring section onto the second reactor building, just 11 months after the same operation on the first reactor.

The installation shows how building an identical copy of the first reactor drives efficiency and saves time. The ring was built 25% more quickly than the same part on unit one, requiring thousands of hours less labour to manufacture. This “replication effect” will benefit the identical Sizewell C project in Suffolk.  The prefabricated ring, which is 47 metres in diameter and 17 metres high, forms a reinforced cylinder around the nuclear reactor.
 
The achievement is all the more impressive as the project deliberately switched materials and labour away from unit two during the pandemic when numbers on site were limited and suppliers were impacted.  This allowed work to focus on areas most critical to the project’s schedule. The optimum construction time between the two reactors at Hinkley Point C is around 12 months and this installation highlights this gap is being maintained.

Simon Parsons, NI Area, Site & Civils Director said: “This significant lift is testament to everyone involved – from the teams who fabricated it, to those on Unit 2 who’ve delivered the civil-works schedule enabling us to install it and also the lifting team themselves. We have continued to learn from Unit 1 to safely deliver a quality product. Well done one and all”.
 

Related articles

HPCDOMELIFT
March 24, 2026

EDF announces leadership changes in its UK nuclear businesses

EDF has named Mark Hartley as the next Chief Executive Officer of the Hinkley Point C nuclear project from 1 July. His appointment comes as current CEO Stuart Crooks steps down from the role after 40 years of service in the nuclear industry.
tunnel boring machine
March 13, 2026

Engineers at Hinkley Point C are ready to start tunnelling the fish return system

Engineers at Hinkley Point C are ready to start tunnelling the second of three fish protection measures at the nuclear power station. The fish return system will be 620m long and 1.8m in diameter.
Sea trials have shown that a new acoustic fish deterrent developed for Hinkley Point C is highly effective.
February 10, 2026

Trials show that Hinkley Point C’s Acoustic Fish Deterrent is Highly Effective 

Sea trials carried out by Swansea University have shown that an acoustic fish deterrent developed for Hinkley Point C is highly effective. The innovative use of ultrasound technology has been shown to keep target fish species away from the power station’s water intakes.