Report into the collapse of a silo at HPC site

By Hinkley Point C media team | Posted May 13, 2021

On 10 June 2020 a Ground Granulated Blast-furnace Slag silo – part of the concrete production facilities at Hinkley Point C - collapsed suddenly and without warning. Following an extensive investigation, the cause of the collapse has been identified and the learnings are being shared with our regulator and the wider industry to avoid such an event occurring elsewhere. The silo was a temporary structure used in construction and not a permanent part of the power station.

In order to help public understanding of the issue we have produced a learning brief, which explains what happened and the steps being taken to learn from the event.

View learning brief

Related articles

Sea trials have shown that a new acoustic fish deterrent developed for Hinkley Point C is highly effective.
February 10, 2026

Trials show that Hinkley Point C’s Acoustic Fish Deterrent is Highly Effective 

Sea trials carried out by Swansea University have shown that an acoustic fish deterrent developed for Hinkley Point C is highly effective. The innovative use of ultrasound technology has been shown to keep target fish species away from the power station’s water intakes. 
Hinkley Point C’s second nuclear reactor has arrived in Somerset
January 12, 2026

Hinkley Point C takes another step forward as its second nuclear reactor arrives in Somerset

The twin nuclear power station at Hinkley Point C has taken delivery of its second nuclear reactor. The first arrived in 2023 and is already installed and welded in place on Unit 1 of the power station.
December 11, 2025

Nigel Cann appointed as Sizewell C Chief Executive Officer as Julia Pyke steps down

Former Hinkley Point C Delivery Director Nigel Cann has been appointed as Chief Executive Officer for Sizewell C. The move follows the decision of joint Managing Director Julia Pyke to leave the project at the end of the year.