On time and built 30% faster – major lift milestone for Hinkley Point C’s second reactor

By Hinkley Point C media team | Posted September 14, 2020

Construction of the second reactor at Hinkley Point C passed a major milestone with the lifting of the first part of the massive steel containment liner. Lifted by the world’s largest crane Big Carl, just nine months after the same lift for the first reactor, construction of the 170-tonne “liner cup” was 30% quicker than the identical part on Unit 1.
 
The liner cup is the base for the reactor’s steel containment which is being prefabricated in five parts and lifted into place by Big Carl.  This innovation means welding can take place in covered bunkers protected from weather, helping to improve quality and efficiency. This is a learning from the construction of other EPR projects around the world. The liner cup for Hinkley Point C’s second unit was built in 39 days versus 57 for the first. The construction and lift were completed on schedule, despite workers having to adapt to Coronavirus working conditions.



The cup is one of more than 500 prefabricated steel and concrete elements that Big Carl will lift, including whole sections of buildings, walls and pre-cast air ducts. The heaviest items weigh in at 1,600 tonnes.
 
Nigel Cann, Hinkley Point C Construction Delivery Director said: “This milestone shows how replication and innovation are driving efficiency at Hinkley Point C as we build our second identical reactor on site. In turn that will benefit our planned third and fourth units at Sizewell C in Suffolk. Hitting the schedule during Coronavirus is a tribute to the workforce that has had to adapt to new ways of working to ensure the safety of the site and the community around it.”

 

Related articles

HPCDOMELIFT
March 24, 2026

EDF announces leadership changes in its UK nuclear businesses

EDF has named Mark Hartley as the next Chief Executive Officer of the Hinkley Point C nuclear project from 1 July. His appointment comes as current CEO Stuart Crooks steps down from the role after 40 years of service in the nuclear industry.
tunnel boring machine
March 13, 2026

Engineers at Hinkley Point C are ready to start tunnelling the fish return system

Engineers at Hinkley Point C are ready to start tunnelling the second of three fish protection measures at the nuclear power station. The fish return system will be 620m long and 1.8m in diameter.
Sea trials have shown that a new acoustic fish deterrent developed for Hinkley Point C is highly effective.
February 10, 2026

Trials show that Hinkley Point C’s Acoustic Fish Deterrent is Highly Effective 

Sea trials carried out by Swansea University have shown that an acoustic fish deterrent developed for Hinkley Point C is highly effective. The innovative use of ultrasound technology has been shown to keep target fish species away from the power station’s water intakes.