By Hinkley Point C media team | Posted April 08, 2020

Last week I said I would keep the community up to date with measures Hinkley Point C is taking to keep the community and our remaining workforce safe during the Coronavirus pandemic. Here is the latest information.

The number of workers on site is being reduced as planned and we will have fewer than 2,000 on site after this week. The reduction from more than 4,000 was done to make social distancing possible. Work is focused on a limited number of critical areas on site and at Combwich where the same strict controls will be in force as on site.

I know that there was some concern about the movement of workers. We have brought in 60 extra buses to enable distancing so that services can run only 30% full. Our drivers are being protected with screens and other safety measures. The move we announced to concentrate bus pick-ups on our controlled park and rides sites is almost complete. We are reminding workers lodged in the local community that moving to our Campus accommodation is a requirement and we are providing this accommodation at no charge.

Many other measures like temperature checks, extra cleaning, hand sanitisers, more space in canteens – and even toilets - remain in place.  Like people all across the country and in the community, workers at Hinkley Point C have shown great personal responsibility in adapting to new behaviours. We will keep listening to our workers, unions and the community and where we can improve, we will.

We are continuing to follow Government and Public Health England advice and we work under the oversight of our independent regulator, the Office for Nuclear Regulation (ONR). Today the ONR has said that it is assured that control measures in place at Hinkley Point C are appropriate.

I know that there are many in the community that depend on Hinkley Point C for their livelihoods through the excellent Somerset companies that provide our food, accommodation and transport. We will continue to support those companies and their workers throughout the crisis. 

I know these are worrying times. If you have any concerns, please contact me or my colleagues. I sincerely wish you and your families the very best for Easter and I will update you again in the near future.
 
Nigel Cann
Construction Delivery Director, Hinkley Point C

Related articles

The tunnel boring machine was named “Sarah Guppy” by local school children after the pioneering 19th century engineer from Bristol
October 01, 2026

Hinkley Point C finishes tunnelling fish return system

Hinkley Point C has just finished digging the 620 metre tunnel for the power station's fish return system, which runs under the Bristol Channel.
Stacy Walker
September 08, 2026

We are Here to Listen: How to Get in Touch with Hinkley Point C

As part of the Hinkley Point C Community Relations team, one of the things I enjoy most about my role is getting out into local communities and talking to people. A question I am often asked is: “How do I actually get in touch with Hinkley Point C?” The good news is, there are lots of ways to contact us – and you don't have to wait for a formal meeting to get involved.
Jack Davies - Quality Assurance Apprentice
August 27, 2026

How is Hinkley Point C benefiting the local community?

Alongside Hinkley Point C’s vital role in providing the country with secure low-carbon electricity, I’m very proud of the significant benefits we provide to our local communities. Maximising the benefits of Hinkley Point C has been a long term collaborative effort, but one which I’m confident will also lead to much longer term opportunity for people and businesses across Somerset and the Sout West.