Major road upgrade finished ahead of schedule

By Hinkley Point C media team | Posted June 29, 2017

A series of major road and junction improvements in Bridgwater have been completed some six weeks ahead of schedule.

The upgrade has included widening the right-turn lane from Bristol Road into The Drove and making the junction safer for pedestrians and cyclists.

Traffic lights have also been upgraded at the Wylds Road junction with The Drove and a left-turn slip road created from Western Way into Wylds Road, together with additional safety improvements for pedestrians and cyclists.

The Drove and Bristol Road have also been resurfaced as part of the work, which has been carried out by EDF Energy as part of a £20 million package of local road improvements in association with its Hinkley Point C project.

Lucy Holt, EDF Energy’s project manager, thanked residents, traders and motorists for their patience during the improvement work.

“We did all we could to lessen the impact of the works, which included a temporary one-way system around the town, and did our best to complete them before the peak summer holiday traffic.

“I would like to thank local people for their patience as well as our contractor, the Somerset Infrastructure Alliance, for working hard to ensure the early completion of the upgrade.” 

The alliance is a collaboration between Bridgwater firm R K Bell Group Ltd, Skanska and Bristol-based Forest Traffic Management Limited. The company is also currently working on a new park and ride facility off the A39 on the outskirts of Cannington to serve the Hinkley Point C site.

Somerset County Councillor David Hall, Cabinet Member for Resources and Economic Development, welcomed the completion of the scheme: “It’s great news that these works have been finished well ahead of schedule because they are essential to helping the flow of traffic in the town.

“Everyone involved has done their best to keep disruption during the works to a minimum and we thank everyone for their patience.”

Cllr Peter Downing, Sedgemoor District Council’s portfolio holder for Infrastructure echoed his sentiments: “The Drove/Wylds Road roadworks were clearly necessary to minimise the impact of Hinkley Point C related traffic through Bridgwater even though some disruption was inevitable.

“As a regular user of that route, my own experience is that the diversions have been well managed

“It is particularly pleasing that the works have now been completed six weeks ahead of schedule and I hope that others will share my appreciation of a job well done.”

Related articles

Hinkley Point C has spent £5.4 billion with 1,500 businesses across the South West
May 26, 2026

New report measures Hinkley Point C’s positive impact on people and the environment

- £20 million of community grants to 385 local organisations - 19,500 people trained in local “Centres of Excellence” - 1,740 apprentices trained – beating a target of 1,000 - £5.4 billion spent with 1,500 businesses across the South West - New factory opened in North Wales to support the project - Suffolk youngsters learn skills to take home to Sizewell C - 65,000 trees planted and 92 bird species identified around the HPC site
Hinkley Point C is preparing for the installation of the second reactor.
May 06, 2026

Under the lid - new video tour takes viewers inside Hinkley Point C’s first reactor

Viewers of Hinkley Point C’s latest video update will get to see inside the first reactor at the nuclear power station in Somerset. The behind the scenes tour from Delivery Director Simon Parsons shows the fit out of Unit 1 accelerating and teams getting ready to install the identical second reactor in Unit 2.
HPCDOMELIFT
March 24, 2026

EDF announces leadership changes in its UK nuclear businesses

EDF has named Mark Hartley as the next Chief Executive Officer of the Hinkley Point C nuclear project from 1 July. His appointment comes as current CEO Stuart Crooks steps down from the role after 40 years of service in the nuclear industry.