The final concrete pour on the foundation of Hinkl...
The final concrete pour on the foundation of Hinkley Point C’s second reactor was completed in last week (June 2020). Work can now begin on the permanent reactor buildings.
The foundation, or Common Raft, is a cross shaped ...
The foundation, or Common Raft, is a cross shaped structure. The fifth and final concrete pour was in the circular centre section.
At just over 9,000m³ the final pour set a new UK ...
At just over 9,000m³ the final pour set a new UK record for the largest continuous concrete pour.
We’ve managed to achieve this milestone during t...
We’ve managed to achieve this milestone during the Coronavirus pandemic. By finding new, safe ways of working, we have been able to keep our site running whilst ensuring the safety of our workforce and community.
Learnings have been taken from Unit 1 – increasi...
Learnings have been taken from Unit 1 – increasing productivity and efficiency. For example, it took 16 hours on Unit 2 to erect a tonne of steel, compared to 25 hours on Unit 1.
Work continues to progress on Unit 1 Nuclear Islan...
Work continues to progress on Unit 1 Nuclear Island where we achieved J0 just 11 months ago.
A range of social distancing measures are in place...
A range of social distancing measures are in place at site, including workforce on site, automatic temperature monitoring, shift rotations and enhanced cleaning protocols .
Celebrating taking part in this major milestone.
Celebrating taking part in this major milestone.