Folders > Hinkley Point C > 3. Archive > 1. Photos by month > 2017.06 - June 2017

2017.06 - June 2017

Cleaning concrete before pouring the final layer i...
Cleaning concrete before pouring the final layer in the southern galleries
Concrete 'blinding' (pouring a thin layer of concr...
Concrete 'blinding' (pouring a thin layer of concrete over the excavated rock formation) in the southern galleries
Engineers check the retaining wall base is aligned
Engineers check the retaining wall base is aligned
Inspection of rock formation level in the southern...
Inspection of rock formation level in the southern galleries
Levelling concrete in the southern galleries
Levelling concrete in the southern galleries
Rock anchors in the southern galleries to ensure s...
Rock anchors in the southern galleries to ensure slope stability
Steel fixers constructing steel reinforcement for ...
Steel fixers constructing steel reinforcement for retaining walls that will support roads and networks
Stressing rock anchors in the southern galleries t...
Stressing rock anchors in the southern galleries to ensure slope stability
Tarmac being laid as part of the construction of t...
Tarmac being laid as part of the construction of the road network for the site
The first sea water cooling pipe segments arrive a...
The first sea water cooling pipe segments arrive at the site on 29 June - each segment weighs 12.8 tonnes
The first sea water cooling pipe segments being sa...
The first sea water cooling pipe segments being safely unloaded
View of the gallery where the first nuclear concre...
View of the gallery where the first nuclear concrete was poured