Built 25% faster - Hinkley Point C's Unit 2 and the "replication effect"

By Hinkley Point C media team | Posted November 16, 2021

Big Carl, the world’s biggest crane has been in action again at Hinkley Point C. It has placed the first huge steel ring section onto the second reactor building, just 11 months after the same operation on the first reactor.

The installation shows how building an identical copy of the first reactor drives efficiency and saves time. The ring was built 25% more quickly than the same part on unit one, requiring thousands of hours less labour to manufacture. This “replication effect” will benefit the identical Sizewell C project in Suffolk.  The prefabricated ring, which is 47 metres in diameter and 17 metres high, forms a reinforced cylinder around the nuclear reactor.
 
The achievement is all the more impressive as the project deliberately switched materials and labour away from unit two during the pandemic when numbers on site were limited and suppliers were impacted.  This allowed work to focus on areas most critical to the project’s schedule. The optimum construction time between the two reactors at Hinkley Point C is around 12 months and this installation highlights this gap is being maintained.

Simon Parsons, NI Area, Site & Civils Director said: “This significant lift is testament to everyone involved – from the teams who fabricated it, to those on Unit 2 who’ve delivered the civil-works schedule enabling us to install it and also the lifting team themselves. We have continued to learn from Unit 1 to safely deliver a quality product. Well done one and all”.
 

Related articles

Hinkley Point C marine works sunrise
February 15, 2024

Tunnels ready for connection to Bristol Channel

Hinkley Point C’s tunnels are ready for the connection to the Bristol Channel to be completed - marking a major step in the construction of the power station’s cooling water system.
site with the dome being put on unit 1 and the words January 2024 update
January 23, 2024

January 2024 project update

Hinkley Point C's Managing Director Stuart Crooks gives an update on the project.
Environment
January 04, 2024

Hinkley Point C sets out plan to create Somerset saltmarsh

Hinkley Point C, the new nuclear power station in Somerset, is asking for views on its plans to create more than 800 acres of saltmarsh on the River Parrett.