Built 25% faster - Hinkley Point C's Unit 2 and the "replication effect"

By Hinkley Point C media team | Posted November 16, 2021

Big Carl, the world’s biggest crane has been in action again at Hinkley Point C. It has placed the first huge steel ring section onto the second reactor building, just 11 months after the same operation on the first reactor.

The installation shows how building an identical copy of the first reactor drives efficiency and saves time. The ring was built 25% more quickly than the same part on unit one, requiring thousands of hours less labour to manufacture. This “replication effect” will benefit the identical Sizewell C project in Suffolk.  The prefabricated ring, which is 47 metres in diameter and 17 metres high, forms a reinforced cylinder around the nuclear reactor.
 
The achievement is all the more impressive as the project deliberately switched materials and labour away from unit two during the pandemic when numbers on site were limited and suppliers were impacted.  This allowed work to focus on areas most critical to the project’s schedule. The optimum construction time between the two reactors at Hinkley Point C is around 12 months and this installation highlights this gap is being maintained.

Simon Parsons, NI Area, Site & Civils Director said: “This significant lift is testament to everyone involved – from the teams who fabricated it, to those on Unit 2 who’ve delivered the civil-works schedule enabling us to install it and also the lifting team themselves. We have continued to learn from Unit 1 to safely deliver a quality product. Well done one and all”.
 

Related articles

HPC Community Fund Networking Event
September 08, 2026

We are Here to Listen: How to Get in Touch with Hinkley Point C

As part of the Hinkley Point C Community Relations team, one of the things I enjoy most about my role is getting out into local communities and talking to people. A question I am often asked is: “How do I actually get in touch with Hinkley Point C?” The good news is, there are lots of ways to contact us – and you don't have to wait for a formal meeting to get involved.
Jack Davies - Quality Assurance Apprentice
August 27, 2026

How is Hinkley Point C benefiting the local community?

Alongside Hinkley Point C’s vital role in providing the country with secure low-carbon electricity, I’m very proud of the significant benefits we provide to our local communities. Maximising the benefits of Hinkley Point C has been a long term collaborative effort, but one which I’m confident will also lead to much longer term opportunity for people and businesses across Somerset and the Sout West.
Parking at Brean Beach
August 14, 2026

Supporting Local Tourism - Free Beach Parking at Brean and Berrow this Summer

Hinkley Point C is helping to make a trip to the seaside a little more affordable this summer by providing free parking at both Brean and Berrow beach car parks. Available throughout the school holidays and into October, the initiative is part of Hinkley Point C’s support for tourism businesses in Brean. The initiative has already proved extremely successful with visitors to the beach more than double the number seen in July last year.