Efficiency improvements drive progress at Hinkley Point C

By Hinkley Point C media team | Posted April 29, 2021

Efficiency improvements drive progress at Hinkley Point C

The world’s largest land-based crane, Big Carl, lifted the second of three massive containment rings from the bunker it was constructed in to a lay-down area close by. Now being prepared for the final lift into the first reactor building, the 17m-tall ring with a diameter of 47m was built 36% faster than the first by teams using the experience gained during the construction of the first ring.

The prefabricated steel ring, which forms part of the reinforced cylinder around the nuclear reactor, was lifted out of a bunker where it was constructed in factory conditions – one of the innovations to improve quality on the project. Prefabrication inside these bunkers reduces the need to work at height or in bad weather and the work can be completed and checked in a controlled setting. 

Big Carl will lift more than 500 prefabricated steel and concrete elements weighing up to 1,600 tonnes.

Liner ring two in numbers…

  • Diameter: 47 metres
  • Height: 17 metres
  • Lifted weight: 308 tonnes
  • Length of welds: 934 metres

Stuart Crooks, Hinkley Point C Managing Director, said: “Our belief that we can do things better drives innovation at Hinkley Point C. As we build the first UK European Pressurised Reactor (EPR) we are learning and improving all the time. This is leading to improved productivity as we build Hinkley Point C’s twin reactors. We will use that experience to underpin our plans for two more identical reactors at Sizewell C.”

Related articles

The tunnel boring machine was named “Sarah Guppy” by local school children after the pioneering 19th century engineer from Bristol
October 01, 2026

Hinkley Point C finishes tunnelling fish return system

Hinkley Point C has just finished digging the 620 metre tunnel for the power station's fish return system, which runs under the Bristol Channel.
Stacy Walker
September 08, 2026

We are Here to Listen: How to Get in Touch with Hinkley Point C

As part of the Hinkley Point C Community Relations team, one of the things I enjoy most about my role is getting out into local communities and talking to people. A question I am often asked is: “How do I actually get in touch with Hinkley Point C?” The good news is, there are lots of ways to contact us – and you don't have to wait for a formal meeting to get involved.
Jack Davies - Quality Assurance Apprentice
August 27, 2026

How is Hinkley Point C benefiting the local community?

Alongside Hinkley Point C’s vital role in providing the country with secure low-carbon electricity, I’m very proud of the significant benefits we provide to our local communities. Maximising the benefits of Hinkley Point C has been a long term collaborative effort, but one which I’m confident will also lead to much longer term opportunity for people and businesses across Somerset and the Sout West.