Skip to main content

Coronavirus update from Hinkley Point C – 15 March

By Nigel Cann - Construction Delivery Director, Hinkley Point C | Posted March 15, 2021

Following the Government’s publication of its roadmap to ease lockdown restrictions, I want to keep you up to date with Hinkley Point C’s plans to keep the community and workforce safe. 

In January, I told you that we were increasing testing as workers returned after the holiday period. Since then we have expanded our mass testing programme in order to stamp out infection at the earliest opportunity. This has helped us uncover and isolate asymptomatic cases which would otherwise not have been recorded. The programme’s effectiveness is highlighted by latest figures which show that of the almost 1,500 tests carried out last week, we found just one asymptomatic infection. 

Meanwhile, all the existing health measures at Hinkley Point C around social distancing, self-isolation, personal behaviour and hygiene remain in place. Falling infection rates show the site is following the steadily improving national and local situation. It is good news that many of our workers and many people in the community are already benefitting from vaccination. The majority of our workforce will have had a first vaccination by the end of April. As national lockdown measures ease, this will offer vital protection to those that need it most. 
 
Despite the good news, I want to assure you that we will not be complacent or simply wait for the virus to go away. The measures we are taking reflect our determination to keep a constant downward pressure on Covid-19.   We will follow Government guidance in planning an end to the lockdown, using a measured step by step process when conditions allow. Like you, we are looking forward to better times and hoping for a return to more normal life. However, as the deputy chief medical officer so memorably put it, no-one should relax until the final whistle is blown, even if the game seems to be going in the right direction.
 
We continue to work closely with Public Health England and our industry regulator, the Office for Nuclear Regulation who recently undertook a site inspection. We are grateful for their constructive and open attitude and pleased that they endorse our approach to tackling infection and stopping transmission.

I will continue to provide you with the latest information and as always, the team and I are here to answer any questions you may have. We are always interested to hear your views on how we can continue to improve.

Nigel Cann
Construction Delivery Director, Hinkley Point C

Related articles

Sea trials have shown that a new acoustic fish deterrent developed for Hinkley Point C is highly effective.
February 10, 2026

Trials show that Hinkley Point C’s Acoustic Fish Deterrent is Highly Effective 

Sea trials carried out by Swansea University have shown that an acoustic fish deterrent developed for Hinkley Point C is highly effective. The innovative use of ultrasound technology has been shown to keep target fish species away from the power station’s water intakes. 
Hinkley Point C’s second nuclear reactor has arrived in Somerset
January 12, 2026

Hinkley Point C takes another step forward as its second nuclear reactor arrives in Somerset

The twin nuclear power station at Hinkley Point C has taken delivery of its second nuclear reactor. The first arrived in 2023 and is already installed and welded in place on Unit 1 of the power station.
December 11, 2025

Nigel Cann appointed as Sizewell C Chief Executive Officer as Julia Pyke steps down

Former Hinkley Point C Delivery Director Nigel Cann has been appointed as Chief Executive Officer for Sizewell C. The move follows the decision of joint Managing Director Julia Pyke to leave the project at the end of the year.